The project timeline

 HUFF OF ARKLOW RESTORATION TIMELINE

Stage 1
August

Complete repairs to frames
Remove remaining old fastenings through horn timber

September 

Repair and renew strap floors aand hanging knees
Fit strap floors and knees (ongoing) 

October

Fit new mast step
Complete re fastening hull

November 

Spline all opened seams
Complete plank repairs

December

Repair covering board
Repair rubbing strake and toe rail

Stage 2

January 2013

Make and fit new fore hatch
Make and fit new lazzerette hatch

February 

Fair hull
Recoat hull, primers, undercoats and top coats

March

Repair or replace companionway beam
Repair stbd bulkhead

April

Remove mainsheet traveller and beam, and make good
Fit mainsheet traveller to after end of cockpit

May

Restore F.U. Lower stem piece
Re fit skeg

June

Fit rudder with tiller stearing
Fit stearing seats

Stage 3

July 

Repair cockpit floor

Re support cockpit floor

August

Repair inner skin
Fit machinery

September 

Fit electric loam
Fit plumbing

October

Fit new starboard 1/4 berth
Fit wet locker in port 1/4
Fit companion way

November 

Finishing off throughout below decks
Cut back after saloon bulkhead and make good
Fit galley
Make new guard rail and pull pit

December 

Fit new guard rail and pull pit
Fit chart table
Refurbish mast

January 2014

Re rig
Fit engine box
Fit out saloon

February 

Fit heads compartment
Fit out forepeak

March - May

Make good
Finishing

June
Launch